How to Turn Estimates into a Realistic Project Timeline

You’ve estimated the effort.
You have person-days by phase.
The next question is: “So how many weeks will this project really take?”

This is where effort meets calendar.
And this is also where many projects slip.

Let’s look at a simple way to convert effort into a realistic, defendable schedule.

Step 1: Start with Effort by Phase

Assume you’ve already estimated person-days for:

  • Requirements
  • Design
  • Development
  • Testing
  • UAT
  • Hypercare

Example:

  • Requirements – 20 PD
  • Design – 15 PD
  • Development – 80 PD
  • Testing – 40 PD
  • UAT – 10 PD
  • Hypercare – 5 PD

Total = 170 PD

This is your effort picture, not yet your calendar picture.


Step 2: Decide Working Days per Week

Keep it simple:

  • 5 working days per week

This gives:

Total weeks (if 1 person did everything) = Total PD / 5

170 / 5 = 34 weeks (obviously not realistic because you’ll have a team).

This is just a baseline.


Step 3: Bring in Team Capacity

Now decide your team composition, for example:

  • 2 developers
  • 1 tester
  • 1 BA / PM support

You don’t need a perfect staffing plan, just a reasonable starting point.


Step 4: Apply Productivity / Boost Factors

Reality is not linear. Adding more people doesn’t always cut effort in half.

So you can define simple productivity boosts:

  • For Design + Development with more developers
  • For Testing with more testers

Example logic:

Adjusted Dev Days = DevDays / (1 + (Developers – 1) × DevBoost%)

If DevBoost is 30% and you have 3 developers:

  • Factor = 1 + (3 – 1) × 0.3 = 1.6
  • Dev phase duration reduces proportionally

Similarly, for testing, you can use a stronger boost (for example 80%) because testing work can be parallelized more.

This gives you a smarter schedule than simply dividing effort by number of people.


Step 5: Keep Phases Sequential (but Practical)

A simple model is:

  1. Requirements
  2. Design
  3. Development
  4. Testing
  5. UAT
  6. Hypercare

Some overlap may be possible in real life, but for a clean baseline schedule:

  • Let each phase start when the previous one ends
  • Later you can overlap based on confidence and risk appetite

This step gives you a clean Gantt-like picture in weeks.


Step 6: Visualize the Schedule in Weeks

Once you know the duration of each phase (in days), you can:

  • Convert to weeks (divide by 5)
  • Map phases to week numbers:

For example:

  • Requirements → Weeks 1–3
  • Design → Weeks 3–5
  • Development → Weeks 5–10
  • Testing → Weeks 10–13
  • UAT → Weeks 13–14
  • Hypercare → Week 15

Even a simple table with rows as phases and columns as weeks gives stakeholders more clarity than just “3 months”.


Step 7: Use a Schedule Generator Instead of Doing It Manually

A Schedule Generator can:

  • Read phase-wise efforts (from your estimator)
  • Take inputs:
    • Developers
    • Dev boost %
    • Testers
    • Tester boost %
  • Calculate adjusted days
  • Convert to weeks
  • Plot phases into a grid
  • Export to CSV or Excel

This reduces the heavy lifting and lets you focus on scenario discussion instead:

  • “What if we add one more developer?”
  • “What if we add another tester?”
  • “What if we reduce UAT duration?”
Here’s a link to PM Toolkit which helps you Estimate Effort easily. PM Toolkit

Step 8: Communicate Schedule as a Range, Not a Single Date

After you generate your baseline schedule, add a realistic view:

  • Best case (if things go smoothly)
  • Likely case (with reasonable delays)
  • Risky areas (integration, environment, third-party dependencies)

Instead of saying:

“We’ll go live on 15th November.”

You can say:

“The plan gives us a 14–16 week window.
With current assumptions, we’re targeting mid-November, with risks around X and Y.”

This feels honest, professional and grounded.

Leave a comment

Your email address will not be published. Required fields are marked *