How to Use GM in Project Management: A Practical Guide for IT Projects

When we talk about project planning, we often focus on scope, timelines, and resources. But there is one number that quietly decides whether a project is truly healthy or not: GM – Gross Margin.

For many project managers, GM feels like “finance territory”. But in real projects, your decisions on scope, effort and change requests directly impact GM. This article is a simple, practical guide to help you understand and use GM in your day-to-day work—without turning into a finance analyst.

GM (Gross Margin) is the difference between revenue and cost, expressed as a percentage of revenue.

GM % = (Revenue – Cost) / Revenue × 100

If revenue is 100 and cost is 70, GM is 30%.
This 30% is what the organization uses for overheads, risks, and profit.

As a project manager, you don’t have to remember complex formulas. You just need to know:

  • Higher GM = more buffer and profitability
  • Lower GM = tight margins, less room for surprises

Even if pricing is done by sales or finance, PMs influence GM every day:

  • When you estimate efforts
  • When you add or ramp up people
  • When you handle scope changes
  • When you approve rework
  • When you delay timelines

Every hour you add to the plan adds cost. Every scope addition without extra revenue reduces GM. Over time, a small slip in estimation can slowly eat up the entire margin.

Understanding GM helps you:

  • Push back on unfunded scope increases
  • Explain the commercial impact of change requests
  • Choose smarter options (reuse, automation) instead of throwing more people at a problem
  • Have more meaningful discussions with sales and finance

Cost, Contingency and Final Cost

In real projects, cost is not just “effort × rate”. We often add contingency for risks and unknowns.

A simple way to think about it:

  • Base Cost = Effort × Rate
  • Contingency % = Extra buffer for risk (for example, 10%)
  • Final Cost = Base Cost × (1 + Contingency%)

When you work with GM, always use Final Cost, not just base cost. This reflects a more realistic view of project risk.

How a PM Can Use a GM Calculator

Instead of calculating this manually every time, you can use a simple GM calculator:

  1. Enter Revenue
  2. Enter Cost
  3. Enter Contingency %
  4. Let the calculator compute:
    • Final cost with contingency
    • GM %

This helps you:

  • See impact of scope changes on GM quickly
  • Compare “option A vs option B” (e.g., 2 senior vs 3 junior resources)
  • Take decisions with both delivery and commercial clarity
Here’s a link to PM Toolkit which helps you calculate GM easily. PM Toolkit

Whenever there is a change request:

  1. Estimate additional effort
  2. Convert to cost
  3. Add contingency
  4. Recalculate GM with new revenue + cost

If the customer pushes for “small changes” without budget, you can show:

  • Impact on schedule
  • Impact on GM

You are no longer just saying “This is risky”, you are showing “This will reduce GM from 28% to 22%”.


GM is Not Just a Finance Number

For a project manager, GM is:

  • A signal of project health
  • A boundary for decision making
  • A language to speak with leadership and sales

You don’t need to become a finance expert.
You just need a simple way to see how your project decisions move GM up or down.

Once you start using GM early in planning and revisit it during execution, it stops being a scary finance term and becomes another useful dial on your project dashboard.